Construction RFI register template

Track each question, responsible recipient, response date, programme impact, answer and resulting action.

No account or email required.

Who owns it

Usually the contract administrator, design manager or project manager responsible for the project RFI process.

When to create it

Create the register entry when the formal RFI is issued and update it when a response, revised response or resulting direction is received.

Field-by-field guide

What to record and why.

FieldWhy it mattersCompleted example
RFI ID and subjectA unique reference and concise issue description.RFI-018 - Level 3 services clash
Date raisedWhen the question entered the formal process.14 July 2026
Raised by / sent toThe originator and responsible recipient.Builder - mechanical consultant
Location and referenceThe area, drawing or specification affected.Level 3 corridor - M-214
QuestionOne direct, answerable question.Confirm revised duct level below Beam B3.
Response requiredThe realistic date needed and programme impact.16 July - ceiling rough-in waiting
Status and response dateOpen, answered, superseded or closed.Answered - 15 July 2026
Resulting actionThe task, instruction or change created by the answer.Update set-out before installation

Common mistakes

  • Combining several questions
  • No drawing or location reference
  • Using an RFI as a hidden variation notice
  • Closing the RFI without recording the resulting action

From template to workflow

The downloadable file helps create a consistent manual record. Only use Convoe for the fields and actions currently supported by the product.

See how the current workflow fits

One site is enough to start

Start with one project. See what your team stops losing.

The crew can keep working in conversation while confirmed tasks, owners, dates and status become visible.