How to record a verbal site instruction before the context disappears

A phone call or site conversation may solve the immediate problem. The record should be created as soon as practical afterwards, using the contract and project procedure that applies.

Last reviewed: 21 July 2026

Reviewed by Dallas, Founder of Convoe
01

Write the direction down promptly

Record the instruction while the wording, location and people involved are still fresh. Make it clear that the note is a record of a verbal direction rather than pretending the instruction was originally written.

Date and time
Who gave the direction
Who received it
Project and exact location
02

Separate the instruction from the commercial question

State the work requested in plain language. Flag possible cost, time or contractual implications for the responsible person instead of hiding them inside the instruction text.

One clear direction
Required date
Potential cost impact
Potential programme impact
03

Confirm responsibility and follow-up

A useful operational record shows who owns the next action and when it is required. In Convoe today, that part can be handled as a human-confirmed task.

Named owner
Due date
Priority
Current status
04

Keep the project procedure in control

A chat message or task does not replace a contractual notice. Follow the required instruction, variation and approval process for the project.

Contract notice
Authorised issuer
Acknowledgement
Commercial review

One site is enough to start

Start with one project. See what your team stops losing.

The crew can keep working in conversation while confirmed tasks, owners, dates and status become visible.